Federal Energy Regulatory Commission (FERC) provides standards for small generation (less than 20 MW) interconnection for facilities within the jurisdiction of the commission. This generally applies to transmission-level interconnection. Distribution-level interconnection is usually regulated by each state's public utilities commission.
The Michigan Public Service Commission (MPSC) has established interconnection agreements and applications for generation up to 20 kW (Category 1) and between 20 kW and 150 kW (Category 2). Updated State Rules for 150 kW to 750 kW (Category 3), 750 kW to 2 MW (Category 4) and greater than 2 MW (Category 5) are under construction. Projects above 150 kW must comply with the original Xcel Energy State Rules as stated in Case No. U-14085. This information can be found in the Projects Greater Than 150 kW section below.
The following links connect to the MPSC Customer Generation application, guidelines and agreement for Category 1 and 2 projects. The last link connects to the MPSC Case No. U-14085, this documentation is used in Projects Greater Than 150 kW section below.
Category 1 and 2 General Site (external link)
Category 1 & 2- Interconnection and Parallel Operating Agreement (Dec. 2012) (PDF)
Xcel Energy (Case No. U-14085) (external link)
Generator Interconnection Procedures (Dec. 2012) (PDF)
Combined Interconnection & Net Metering Application (PDF)
Generator Interconnection & Net Standards (2009 AACS) (PDF)
Combined Interconnection & Net Metering Application (PDF)
This section is for projects above 150 kW and must comply with the original Xcel Energy State Rules as stated in Case No. U-14085.
Interconnection Requirements (5/2004) (PDF)
Interconnection Process for Distributed Generation Systems
Interconnection Process
Process Flow Chart
Interconnection Application
Engineering Data Submittal and Agreement
Interconnection Agreement
Michigan Tariffs relating to distributed generation can be found in the below sections of the Michigan Electric Rate Book.
General Michigan Rates and Tariffs (MPSC No. 2- Electric; 6/2013) (PDF)
Net Metering up to 20kW (Sheet No. D-41.0)
Net Metering 20kW to 150kW (Sheet No. D-44.0)
Parallel Generation - Methane Digesters 150kW to 550kW (Sheet No. D-47.0)
Standby, Maintenance and Supplemental Services Rider (Sheet No. D-48.0)
Optional Standby and Optional Maintenance Rider (Sheet No. D-49.0)
Wheeling Service Rider (Sheet No. D-50.0)
Call Center: 1-800-895-4999
Deb Erwin, Manager - Regulatory Policy: deborah.e.erwin@xcelenergy.com
Federal Energy Regulatory Commission (FERC) provides standards for small generation (less than 20 MW) interconnection for facilities within the jurisdiction of the commission. This generally applies to transmission-level interconnection. Distribution-level interconnection is usually regulated by each state's public utilities commission.
The Colorado Public Utilities Commission has set standards for interconnection and net metering of distributed generation in the document 4 Code of Colorado Regulations (CCR 723-3). The flow charts below provide high level guidance to interconnection processes required by Rule 3667 of CCR 723-3.
Colorado State Rules (12/2017) (PDF)
Net Metering Information, Rule 3664
Community Solar Gardens, Rule 3665
Small Generation Interconnection Procedures, Rules 3667 (up to 10MW)
Small Power Producers and Cogeneration, Rule 3900-3918 (over 10 MW)
Tariff Book (6/2018) (PDF)
Net Metering Service- Sheet No. 112
Photovoltaic Service - Sheet No. 113
Solar Rewards Community Service - Sheet No. 114
Secondary Photovoltaic Time-of-Use Service - Sheet No. 49
Small Power Production and Cogeneration - Sheet No. P1-P7
Generator Soft Load Transfer Interconnection Agreement (2/2015) (PDF)
Interconnection Requirements (PDF) - DG Manual
Storage Guidance 1 (Non-Renewable) (PDF)
Storage Guidance 2 (Renewable, Utility-side of Production Meter) (PDF)
Storage Guidance 3 (Renewable, PV-side of Production Meter) (PDF)
Declaration Form 1A and 2A (PDF)
Declaration Form 1B and 1C (PDF)
Declaration Form 2B and 2C (PDF)
Declaration Form 3A and 3B (PDF)
Call Center: 1-800-895-4999
Thomas Malone, Engineer: thomas.h.malone@xcelenergy.com
Jennifer Bass, Transmission Account Representative: jennifer.l.bass@xcelenergy.com
Federal Energy Regulatory Commission (“FERC”) provides standards for small generation (less than 20 MW) interconnection for facilities within the jurisdiction of the commission. This generally applies to transmission-level interconnection. Distribution-level interconnection is usually regulated by each state's public utilities commission.
Links to the current PUCT rules relating to Distributed Generation are below. A Distributed Generation Interconnection Manual was created by the PUCT to be used with the current rules. For more information about the interconnection manual see the Interconnection Forms and Agreements section below.
Texas tariffs relating to distributed generation can be found in section IV of the Texas Electric Rate Book.
Xcel Energy Texas Electric Rate Book (Rev. 119) (PDF)
Section IV-77 - Electric Service to a Qualifying Facility of Aggregate Generation Capacity of 100 kW of Less
Section IV-86 - Energy Purchase from a Qualifying Facility of Aggregate Generating Capacity of 100 kW of Less
Section IV-117 - Avoided Energy Cost Non-Firm Purchases from Qualifying Facilities
Section IV-159 - Distributed Generation Interconnection
Section IV-179 - Primary QF Standby Service
Section IV-180 - Secondary QF Standby Service
Steven Hudson
Xcel Energy Texas & New Mexico Principal Engineer
790 S. Buchanan St.
Amarillo, TX 79101
Phone: 806-378-2165
Email: Steven.Hudson@xcelenergy.com
Annette Gallegos
Principal Transmission Representative
Phone: 806-640-6302
Email: Annette.Gallegos@xcelenergy.com
Federal Energy Regulatory Commission (FERC) provides standards for small generation (less than 20 MW) interconnection for facilities within the jurisdiction of the commission. This generally applies to transmission-level interconnection. Distribution-level interconnection is usually regulated by each state's public utilities commission.
The New Mexico state interconnection rules as adopted by the New Mexico Public Regulation Commission (PRC) are report in rules 568, 569, 570, and 572.
New Mexico Tariffs relating to distributed generation can be found in the below sections of the New Mexico Electric Rate Book.
Xcel Energy New Mexico Tariffs (PDF) (8/2014)
Requirements applying to interconnections less than or equal to 10MW as referenced in state rule 568 are including below in the New Mexico Interconnection Manual. The manual includes interconnection process, agreements, and applications. Separated documents are also included below. All transmission interconnection guidelines must comply with the following guidelines in addition to FERC requirements.
Contents of the New Mexico Interconnection Manual (July 2008) (PDF) include:
NM Energy Storage Diagrams 1A, 1B, 1C, 2A, 2B, 2C, 3A, 3B (PDF)
Xcel Energy NM Electric Energy Storage Interconnection Guidelines (PDF)
The following link connects to the Xcel Energy Interconnection Manual, the Public Regulation Commission Manual can be found in the New Mexico Interconnection Documents section above.
Xcel Energy New Mexico Interconnection Manual (10/2009) (PDF)
Call Center: 1-800-895-4999
Annette Gallegos, Principal Transmission Representative: annette.gallegos@xcelenergy.com
Steven Hudson, Principal Engineer: steven.hudson@xcelenergy.com
Impact Studies are performed in a “cluster” method twice a year in April and October. SPS will require the party requesting interconnection to provide initial funding in the amount of $30,000 to determine if upgrades will be needed to the effected transmission system. All funding and DG generator interconnection information must be provided to SPS no less than 30 days prior to April or October. Impact Studies typically take four to six months to be completed. Multiple studies and additional funding are always a possibility. After the SPP Impact Study process is completed and provided to SPS, SPS will contact the party requesting interconnection with any transmission system upgrades required along with the distribution system upgrades. If any funding is not used for the Impact Study, it will be refunded to the party requesting interconnection.
Distributed generation in excess of the net distribution load on a substation will result in power flowing into the transmission system. Net distribution load is the sum of the traditional load and any pre-existing generation under normal operating conditions. For this situation, the substation is considered an impact to the transmission system and could require upgrades. Facilities 2 MW and less may be eligible for the fast track process in lieu of the DSIS.
SPS shall have the option to enter into the applicable Affected System study agreements and to be financially responsible for such studies, or as a condition of interconnection, to require the interconnection customer to submit a request to enter the DSIS process or other SPP study process as applicable.
Generator interconnections to the Southwestern Public Service Company (“SPS”) distribution system, not subject to Southwest Power Pool (“SPP”) Open Access Transmission Tariff (“OATT”), may still require studies to identify impacts on SPS’s transmission system. SPS will notify SPP of interconnection requests of 5 MW or more to be studied pursuant to SPP’s Affected System Generation Interconnection Impact study process (“Impact Study or Studies”). SPP and/or SPS will evaluate each interconnection request not subject to OATT requirements and will make the final determination whether the interconnection impact study will be performed by SPP. In instances where further study is warranted, such studies will be performed by SPP, at the direction of SPS. Non-jurisdictional generator interconnection customers may be required to enter into the appropriate study agreements with SPP to facilitate an Affected System Agreement. Additionally, requests for non-jurisdictional generator interconnections may be required to be coordinated with SPP in accordance with North American Electric Reliability Corporation (“NERC”) standards.
Although such studies may be performed within SPP’s Generation Interconnection Process (“GIP”) for planning purposes, the non jurisdictional generator interconnection customer will not be subject to the OATT. In such instances, the following shall apply:
1. When notified, SPP is responsible for conducting any required studies to determine if the request may impact the Transmission System.
2. Should SPP determine that the generator interconnection may impact the Transmission System, SPP shall notify SPS of such impacts and provide to SPS any system impact studies that detail such impacts.
3. As an impacted system, SPP will determine what additional studies will be required to coordinate the impacts, up to and including studying the impact in the Definitive Interconnection System Impact Studies (“DSIS”). SPS shall require as a condition of interconnection with the generation customer making request for interconnection, that all SPP required studies be completed. SPS shall have the option to enter into the applicable Affected System study agreements and to be financially responsible for such studies, or as a condition of interconnection, to require the interconnection customer to submit a request to enter the DSIS process or other SPP study process as applicable.
4. It shall remain SPS’s responsibility to complete any generator interconnection agreements in accordance with SPS’s generator interconnection procedures regarding the completion of Network Upgrades required on the Distribution System and on SPS’s Transmission System.
Federal Energy Regulatory Commission (FERC) provides standards for small generation (less than 20 MW) interconnection for facilities within the jurisdiction of the commission. This generally applies to transmission-level interconnection. Distribution-level interconnection is usually regulated by each state's public utilities commission.
The North Dakota state interconnection rules as adopted by the North Dakota Public Service Commission are report in rules 69-09-02, 69-09-07, and 69-09-08.
General ND PSC Article 69-09 (external link)
Standards of Service - Electric (69-09-02)(2017)(PDF)
Small Power Production and Cogeneration (69-09-07)( 1991)(PDF)
Renewable Electricity and Recycled Energy Tracking System (69-09-08)(2011)(PDF)
North Dakota Tariffs relating to distributed generation can be found in Section 9, Cogeneration and Small Power Production, of the North Dakota Electric Rate Book. Tariffs relating to Standby Rates can be found in Section 5-82, Standby Service Rider.
North Dakota Electric Rate Book: Section 9 (PDF) - Cogeneration and Small Power Production (2/2014)
North Dakota Electric Rate Book: Section 5 (PDF) – Standby Service Rider (5/2014)
North Dakota Service Offerings & Rates
A detailed description of the interconnection process can be found in the document, Distributed Generation Interconnection Manual, below. The manual also includes an interconnection process flow chart, interconnection application and agreement, an engineering data submittal form, and interconnection requirements.
Call Center: 1-800-895-4999
John Wold, Program Manager: john.c.wold@xcelenergy.com
Cory Kiemele, Distribution Engineer: cory.f.kiemele@xcelenergy.com
Gregory Gorski, Transmission Account Representative: gregory.e.gorski@xcelenergy.com
Federal Energy Regulatory Commission (FERC) provides standards for small generation (less than 20 MW) interconnection for facilities within the jurisdiction of the commission. This generally applies to transmission-level interconnection. Distribution-level interconnection is usually regulated by each state's public utilities commission.
The South Dakota State interconnection rules as adopted by the South Dakota Public Utilities Commission, Administrative Rules 20:10:36.
South Dakota Tariffs relating to distributed generation can be found in Section 9, Cogeneration and Small Power Production, of the South Dakota Electric Rate Book. Tariffs relating to Standby Rates can be found in Section 5-68, Standby Service Rider.
Section 9 - Cogeneration and Small Power Production (11/2013) (PDF)
Section 5-68- Standby Service Rider (5/2013) (Go to page 59) (PDF)
The applicable forms and agreements are found in the state rules. Below are links for rues and forms along with the interconnection manual for SD-PUC and Xcel Energy.
Xcel Energy Distributed Generation Interconnection Manual (May 2012) (PDF)
South Dakota PUC Distributed Generator Interconnection Rules and Forms (May 2009) (Go to page 66) (PDF)
Xcel Energy Storage Interconnection Guidelines (PDF)
Energy Storage System Configuration Diagrams (PDF)
Call Center: 1-800-895-4999
John Wold, Program Manager: john.c.wold@xcelenergy.com
Cory Kiemele, Distribution Engineer: cory.f.kiemele@xcelenergy.com
Gregory Gorski, Transmission Account Representative: gregory.e.gorski@xcelenergy.com
Impact Studies are performed in a “cluster” method twice a year in April and October. SPS will require the party requesting interconnection to provide initial funding in the amount of $30,000 to determine if upgrades will be needed to the effected transmission system. All funding and DG generator interconnection information must be provided to SPS no less than 30 days prior to April or October. Impact Studies typically take four to six months to be completed. Multiple studies and additional funding are always a possibility. After the SPP Impact Study process is completed and provided to SPS, SPS will contact the party requesting interconnection with any transmission system upgrades required along with the distribution system upgrades. If any funding is not used for the Impact Study, it will be refunded to the party requesting interconnection.
Distributed generation in excess of the net distribution load on a substation will result in power flowing into the transmission system. Net distribution load is the sum of the traditional load and any pre-existing generation under normal operating conditions. For this situation, the substation is considered an impact to the transmission system and could require upgrades. Facilities 2 MW and less may be eligible for the fast track process in lieu of the DISIS.
SPS shall have the option to enter into the applicable Affected System study agreements and to be financially responsible for such studies, or as a condition of interconnection, to require the interconnection customer to submit a request to enter the DSIS process or other SPP study process as applicable.
Generator interconnections to the Southwestern Public Service Company (“SPS”) distribution system, not subject to Southwest Power Pool (“SPP”) Open Access Transmission Tariff (“OATT”), may still require studies to identify impacts on SPS’s transmission system. SPS will notify SPP of interconnection requests of 5 MW or more to be studied pursuant to SPP’s Affected System Generation Interconnection Impact study process (“Impact Study or Studies”). SPP and/or SPS will evaluate each interconnection request not subject to OATT requirements and will make the final determination whether the interconnection impact study will be performed by SPP. In instances where further study is warranted, such studies will be performed by SPP, at the direction of SPS. Non-jurisdictional generator interconnection customers may be required to enter into the appropriate study agreements with SPP to facilitate an Affected System Agreement. Additionally, requests for non-jurisdictional generator interconnections may be required to be coordinated with SPP in accordance with North American Electric Reliability Corporation (“NERC”) standards.
Although such studies may be performed within SPP’s Generation Interconnection Process (“GIP”) for planning purposes, the non jurisdictional generator interconnection customer will not be subject to the OATT. In such instances, the following shall apply:
1. When notified, SPP is responsible for conducting any required studies to determine if the request may impact the Transmission System.
2. Should SPP determine that the generator interconnection may impact the Transmission System, SPP shall notify SPS of such impacts and provide to SPS any system impact studies that detail such impacts.
3. As an impacted system, SPP will determine what additional studies will be required to coordinate the impacts, up to and including studying the impact in the Definitive Interconnection System Impact Studies (“DSIS”). SPS shall require as a condition of interconnection with the generation customer making request for interconnection, that all SPP required studies be completed. SPS shall have the option to enter into the applicable Affected System study agreements and to be financially responsible for such studies, or as a condition of interconnection, to require the interconnection customer to submit a request to enter the DSIS process or other SPP study process as applicable.
4. It shall remain SPS’s responsibility to complete any generator interconnection agreements in accordance with SPS’s generator interconnection procedures regarding the completion of Network Upgrades required on the Distribution System and on SPS’s Transmission System.
Federal Energy Regulatory Commission (FERC) provides standards for small generation (less than 20 MW) interconnection for facilities within the jurisdiction of the commission. This generally applies to transmission-level interconnection. Distribution-level interconnection is usually regulated by each state's public utilities commission.
The Wisconsin Public Service Commission has set Rules for Interconnecting Distributed Generation Facilities in the Wisconsin Administrative Code Chapter PSC 119.
Wisconsin Electric Rules - PSC 119 (1/2017, No. 733)
Service Rules for Electrical Utilities - PSC 113 (7/2014, No. 703) (PDF)
Wisconsin tariffs relating to distributed generation can be found in the Wisconsin Electric Rate Book.
Wisconsin Distributed Resources Collaborative worked with stakeholders in 2018 and 2019 to update and streamline the distributed generation interconnection application process in Wisconsin under Wis. Admin. Code ch. PSC 119. New, reorganized interconnection application forms are now available for use beginning January 1, 2020.
The new forms should be used in place of the previous application forms, known as forms 6027 and 6028. The new forms consist of one single base application form, and a series of technology specific attachments. The forms are designed to streamline the information requested from DG interconnection applicants, eliminating information deemed unnecessary that was included on the earlier forms.
Wisconsin Standard Distributed Generation Interconnection Form (Up to 15 MW)
Solar Photovoltaic Supplement
Wind Turbine Supplement
Generator Supplement
Energy Storage Supplement
Change of Ownership Form
For Energy Storage applications, see additional information below.
Guidelines for Interconnection of Electric Energy Storage (PDF)
Energy Storage Diagrams (PDF)
Energy Storage Questionnaire (PDF)
WI Declarations 1A & 2A (PDF)
WI Declarations 1B & 1C (PDF)
WI Declarations 2B & 2C (PDF)
WI Declarations 3A & 3B (PDF)
Guidelines have also been established by the Wisconsin Distributed Resources Collaborative. These guidelines include a detailed description of the application process for interconnection and a process flow chart.
The Public Service Commission of Wisconsin has established interconnection agreements for generation up to 20kW and between 20kW and 15MW.
Interconnection Agreement (up to 20kW) (9/2011) (external PDF)
Interconnection Agreement (20kW to 15MW) (9/2011) (external PDF)
Parties interested in evaluating a potential distribution system interconnection may for a non-refundable fee of $300 request a Pre-Application Report of certain information about the proposed Point of Common Coupling.
For information on Pre-Application Reports, including the process for requesting a report, contact DERInterconnectionWI@xcelenergy.com.
1-800-895-4999
You have been selected to participate in a brief survey to help us improve our site.
By selecting YES, an additional window will open to allow you to take the survey at the conclusion of your visit. Please do not close it if you would like to participate.