Interconnection Guidelines For Parallel Operation of Distribution Connected Customer-Owned Generation
This information applies to Xcel Energy service territories in Minnesota
It is Xcel Energy’s policy to facilitate any distributed generation consistent with federal, state, and tariff requirements that can be connected and operated safely.
NOTE: The Standard Interconnection and Power Purchase Tariff for 10 MW or less became effective on July 14, 2006. The Standard Interconnection and Power Purchase Tariff for 2 MW or less will be closed upon approval by the Minnesota Public Utilities Commission. Additionally, the Small Wind Tariff will be updated to utilize the interconnection requirements and standards in the 10 MW Tariff.
The following are links to Xcel Energy’s tariffs; after accessing the tariff, see the bookmarks on the left for each tariff.
-
-
-
-
General Distributed Generation Tariff; Tariff Section 9, 0-40 kW net energy, purchase & sale billing, time of day purchase service, rules for cogeneration and small power production facilities.
-
If you have questions concerning Distributed Generation interconnections in Minnesota, please call Xcel Energy’s Business Solution Center at 1-800-481-4700 to contact our Area Engineer for your area.
The interconnection of distribution connected customer-owned generation with configurations and sizes not covered by the tariffs above may be feasible. These situations should be discussed with our Area Engineer for your area.
|