Xcel Energy has begun construction on its first new coal-fired electric generation unit in nearly 30 years. Comanche Station near Pueblo, Colorado, is the site for our 750-megawatt generating unit. The new unit will use a highly efficient supercritical boiler and all units will have state-of-the art emission controls. We will more than double the plant's electricity output while improving overall air quality. To help you quickly find what you’re looking for, here are some links.

Are you…

 

Comanche station - proposed Unit 3 at right - click for larger image
Photo simulation of Comanche station, with the proposed Unit 3 at right

 

Construction employees battle weather to remain on schedule

To borrow from the U. S. postal service motto, it may be said that neither snow, nor rain, nor heat, nor gloom of night stays the brave workers of Comanche 3 from the swift completion of their appointed tasks. For despite brutal weather conditions over the past nine months, construction on Comanche 3 is on schedule and commercial operation should began on time in Fall 2009.

There are three major components on a project such as this: engineering, procurement and construction. As with any project, engineering and design leads the way. Comanche 3 engineering is now 84 percent complete. Procurement of materials is well ahead of schedule at 95 percent completion, even with material shortages and tight manufacturing deadlines.

As mentioned, despite weather obstacles, project construction is on schedule and 22 percent complete. A series of winter weekend snowstorms and an unusually wet spring created what can only be described as difficult working conditions that construction crews managed to overcome. Of special note, over 60 percent of the Unit 3 boiler structural steel has been erected. Also, the boiler steel has reached its highest point and when it is completed in the fall of this year it will consist of over 6,750 tons of steel. The erection of the scrubber vessels for Units 1, 2 & 3 is progressing well and the stack is complete.

Also, currently there are over 900 workers on site. While attracting a qualified labor force remains a challenge due to a nationwide labor shortage, (see accompanying article), we will continue hiring to meet a projection of a peak of over 1,400 on site by the end of this year.

 

For more information on Comanche Station, visit the links below:

 

Comanche 3 Generator Installation Resource
The generator stator is ready for installation.

 

Comanche 3 Construction scene
Construction tradesman at work on Comanche 3.

 

Comanche 3 WS
Work continues on the steam turbine pedestal.

 

Plant Partners and Contractors

As with any major construction project, Comanche 3 will be built through the expertise and teamwork of Xcel Energy, its partners, and contract specialists such as these.

Intermountain Rural Electric Association

Intermountain Rural Electric Association (IREA)  of Sedalia, Colo., will own about 25 percent of the output, estimated to be about 190 megawatts.

Holy Cross Energy

Holy Cross Energy is another project partner. It will own about eight percent of the output, estimated to be about 60 megawatts.

Shaw Stone & Webster

The contract for the engineering, procurement, and construction portion of Comanche 3 has been awarded to Shaw Stone & Webster of Baton Rouge, Louisiana. Shaw’s contract includes the erection of the steam turbines, and supplying and erecting associated plant systems, including piping, pumps, heat exchangers, and electrical equipment. In addition, Shaw will be involved with the engineering and installation of concrete foundations and other civil and electrical works for the plant.

The Babcock & Wilcox Company

The Babcock & Wilcox Company (B&W) has received a contract for engineering, materials, and start-up commissioning of three dry flue gas desulphurization (FGD) units. B&W will supply the FGD systems, commonly called scrubbers, for each unit, including mercury removal sorbent injection systems, ash recycle systems, flue work, and structural steel, as well as a common pebble-lime unloading and storage system and a common lime-slaking system. B&W also will supply a pulse jet fabric filter and induced draft fans will also be supplied as well as construction services.

ALSTOM

Xcel Energy has awarded ALSTOM the contract to design, supply, erect and commission a high-efficiency, supercritical boiler for the company’s planned 750 MW Comanche 3 generating unit. Alstom is a global leader in power generation and rail transport infrastructure.

Mitsubishi Heavy Industries

We’ve also selected Mitsubishi Heavy Industries (MHI) to supply the turbine for Comanche 3. MHI is a global provider of products and services for the power and engineering, transportation and security, and other industries.

Hiring Information

For information about construction jobs building Comanche 3, contact the Colorado Building and Construction Trades Council at 303-936-3301.

Project Timeline

Xcel Energy announced plans to build Comanche 3 in Least-Cost Resource Plan 

April 30, 2004

Colorado Public Utilities Commission approved Comanche 3

January 21, 2005

Xcel Energy requested permission to build new transmission link 

February 16, 2005

Labor Agreement reached 

June 9, 2005

All necessary permits received September 30, 2005
Site preparation work begins September 2005
Primary contractor selected January 2006
Construction begins on unit 3 January 2006

Construction begins on unit 1 and 2 emissions controls 

Fall 2006

Units 1& 2 emissions controls installed

November 2008

Transmission line in service 

May 2009

Unit 3 construction complete and in-service

Fall 2009

Environmental Controls

Comanche Unit 3 will feature state-of-the-art emission controls. We will also install additional emission controls both on the two existing units at the plant. As a result, overall sulfur dioxide (SO2) and nitrogen oxide (NOx) emissions at Comanche Station will be lower than they are today, even when electric generation at the entire facility more than doubles.

For more information about the environmental controls planned for Comanche 3, download the air permit fact sheet (439K PDF) or the environmental settlement fact sheet (44K PDF). For complete information about air emissions performance please see the Comanche Station Air Emissions page.

Low Water Use

A low water use system for Comanche Unit 3 will use both water and air for cooling, which reduces water use by about half. The Pueblo Water Board has determined that adequate water supplies are available for the new unit.

Local Economic and Environmental Benefits

Project cost 

$1.3 billion

Labor costs  

$250 million

Costs for additional emissions controls on existing units 1 and 2

$127.9 million

Construction jobs  

1,000

Additional full-time plant jobs  

40

Total Annual air emissions reductions

10,000 Tons Sulfur Dioxide
2,5000 Tons Nitrogen Oxide

Initial tax payment to the City of Pueblo 

$13 million

Annual tax payments to Pueblo during the first ten years of operation 

$10 million

Current annual taxes to Pueblo (includes County, City, special districts and schools)

$4.5 million

Donation for school districts for diesel emissions reductions on buses 

$250,000

Donation to Colorado Department of Public Health and Environment for mercury reduction efforts at Rocky Mountain Steel

$100,000

Power Use

The new unit at Comanche Station will serve customers in Colorado. That includes Xcel Energy’s residential and business customers as well as our wholesale customers, including: Aquila in Pueblo, Holy Cross Energy in Glenwood Springs, Grand Valley Power in Grand Junction, Yampa Valley Electric in Steamboat Springs, Intermountain REA in Sedalia, and the cities of Julesburg, Burlington and Center.

 